CISG article 49:

"(1) The buyer may declare the contract avoided:
(a) if the failure by the seller to perform any of his obligations under the contract or this Convention amounts to a fundamental breach of contract; or
(b) in case of non-delivery, if the seller does not deliver the goods within the additional period of time fixed by the buyer in accordance with paragraph (1) of article 47 or declares that he will not deliver within the period so fixed."


Here we find the traditional "fundamental breach" standard of the general contract law, which we referred to in yesterday's post.

The above article 49 should be read in connection with article 33 which states:

"The seller must deliver the goods:
(a) if a date is fixed by or determinable from the contract, on that date;
(b) if a period of time is fixed by or determinable from the contract, at any time within that period unless circumstances indicate that the buyer is to choose a date; or
(c) in any other case, within a reasonable time after the conclusion of the contract.
"

Hey, where is my pizza? I am hungry!Ok, but how about my pizza, then? Remember?

Write a comment

New comments have been disabled for this post.

March 2014
M T W T F S S
February 2014April 2014
1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 30
31